Calculation #1 (labor and material needs) 🏠

BY: @kharrazi | CREATED: Oct. 3, 2017, 5:21 p.m. | VOTES: 76 | PAYOUT: $14.72 | [ VOTE ]

https://steemitimages.com/DQmc8knpVyqcnjLTr4xQmyzTzr4HnwZTSoXc4qYthP5oCKe/DSC03441%20copy.jpgGreetings, how are you steemit friends? Glad to see you again and hopefully keep the spirit.
Today I will discuss about the application of the labor and material needs I have previously discussed and I will exemplify to the building we are planning.

In the previous discussion we have discussed about the needs of labor and materials on the work of excavation, backfill, foundation, walls, reinforced concrete work and other work.

In accordance with the picture below then we will calculate the needs of labor and materials needed.

https://steemitimages.com/DQmcg1VoQeV3kJUhZwneLGdVe5wVaRh3Wer9iDSVLDrufsB/DENAH.jpg
credit @kharrazi
https://steemitimages.com/DQmaQdw112pfTFBVFnFU4fXMBZTPikf9iZc5HhwkQUFG757/TAMPAK%20A.jpg
credit @kharrazi
https://steemitimages.com/DQmWv6wvXQTDU2i2yW3cSAHUNp38b4HkFm3NYdcgYNPQC2S/TAMPAK%20B%2CC%2CD.jpg
credit @kharrazi
https://steemitimages.com/DQmRu8CV8uMqkawB4PvmJhBhxDH66DEpPjyZtmutG9qaiXV/POT%20A.jpg
credit @kharrazi
https://steemitimages.com/DQmaid7n4foHGjCaHj8b8xG3j15oMj7K4eRzNiB9KDxkEez/DENAH%20PONDASI.jpg
credit @kharrazi
https://steemitimages.com/DQmRVn6o2LUwRSzq8gKfkQbgDWjCX4FQjvANbL69Xx7nxJp/DETAIL%20PONDASI.jpg
credit @kharrazi
https://steemitimages.com/DQmYEbU5MzRRKnRvPKPUg8eeHfJ9ciUYSawqKeWWvaLPnrW/SLOOF%201.jpg
credit @kharrazi
https://steemitimages.com/DQmSjPSRwe1bEipxvAzCaTcoSxi5js1ZdUhdsCaewFq4t2P/KOLOM%201.jpg
credit @kharrazi

The work we will count is
- Soil excavation work [1] [2]

The form of excavation is carried out in accordance with the one shown in the drawing, If at the place of excavation found pipe disposal or wires that are still working then you should immediately notify the authorized agency to get further instructions.

Backfill work is done with upcoming ground, backfill done several layers, then each layer is compacted with compactor and others, to produce maximum density and no decrease of floor.

Backfill work under the floor is done after excavation work foundation soil is completed

'- Stone pairs [3]

Stone used comes from rivers or mountains with shapes and sizes corresponding to the cross section to be worked on, the stone must be clean of mud and other organic substances that can damage the structure.

Mountain rock used in this work must be really hard, strong, clean, free of cracks and should come from reliable sources of retrieval. Prior to installation, the stone must be moistened with water between three and four hours before use in such a way that each stone is fully exposed to water.

Slab dim. 15/20 cm
The reinforced steel that has been produced must match the drawing of the plan.
Installation of previously manufactured formwork must be appropriate to the size of the slab and the side-support pair as a binder. Installation should be straight and strong so as not to melt at the time of casting. The casting in accordance with the proportion of the mixture.

Column (Practical column) dim. 13x13 cm [5]

The making of marks on the basis should be precise on the axles specified in accordance with the plan.
The reinforcement and brace columns must match the image. Installation of special formwork on double-sided practical columns (formerly formwork oiled) and reinforced with reinforcing wood on column sides.

Bricks are soaked for a few minutes in water to prevent the cement from being absorbed by the bricks so that the adhesion will decrease.
Preparing the mounting position on the column to position the masonry correctly and in accordance with the drawing plan.

QUESTION

In accordance with the picture above, how much labor and materials needed to complete the works?

ANSWER

I use technical analysis in accordance with Indonesian National Standard to complete the calculation of labor and material requirements. [8]

Is known.
Information | Amount
-|-|
Length x width x height | 16.00 x 0.70 x 0.70
Amount | 7,840 m3

Coefficient of 1m3 excavation of soil.
Information | Amount
-|-|
Workers | 0.750 Person per day
Overseer | 0.025 Person per day

Amount as needed
Items | Information | Amount
-|-|-|
Workers | 0.750 Person per day x 7,840 m3 | 5,880 Person
Overseer | 0.025 Person per day x 7,840 m3 | 0.196 Person

Volume a (backfill foundation work)
Is known.
Information | Amount
-|-|
1/3 backfill | 7,840 / 3
Amount | 2,613 m3

1m3 backfill coefficient a
Information | Amount
-|-|
Workers | 0.750 Person per day
Overseer | 0.025 Person per day

Amount as needed

Items | Information | Amount
-|-|-|
Workers | 0.750 Person per day x 2,613 m3 | 1,960 Person
Overseer | 0.025 Person per day x 2,613 m3 | 0.065 Person

Volume b
Is known.
Information | Amount
-|-|
Length x width x height | 3.85 x 3.85 x 0.10
Amount | 1,482 m3

1m3 backfill coefficient
Information | Amount
-|-|
Workers | 0.300 Person per day
Overseer | 0.010 Person per day
Soil | 1,200 M3

Amount as needed
Items | Information | Amount
-|-|-|
Workers | 0.300 Person per day x 1,483 m3 | 0.445 Person
Overseer | 0.010 Person per day x 1,483 m3 | 0.015 Person
Soil | 1,200 x 1,483 m3 | 1,779 m3

Volume Sandfill work
Is known
Information | Amount
-|-|
Length x width x height | 3.85 x 3.85 x 0.05
Amount | 0.741 m3

Coefficient of 1m3 sandfill work.
Information | Amount
-|-|
Workers | 0.300 Person per day
Overseer | 0.010 Person per day
Sand | 1,200 M3

Amount as needed
Items | Information | Amount
-|-|-|
Workers | 0.300 Person per day x 0.741 m3 | 0.222 Person
Overseer | 0.010 Person per day x 0.741 m3 | 0.007 Person
Sand | 1,200 x 0.741 m3 | 0.887

Volume stone pairs work
Is known.
Information | Amount
-|-|
Length x width x height | 16.00 x 0.70 x 0.10
Amount | 1,120 m3

Coefficient of 1m3 stone pairs is required.
Information | Amount
-|-|
Workers | 0.780 Person per day
Stonemason | 0.390 Person per day
Foreman | 0.039 Person per day
Overseer | 0.044 Person per day
Mountain rock | 1,200 m3
Sand | 0.432 m3

Amount as needed.
Items | Information | Amount
-|-|-|
Workers | 0.780 Person per day x 1,120 m3 | 0.874 Person
Stonemason | 0.390 Person per day x 1,120 m3 | 0.437 Person
Foreman | 0.039 Person per day x 1,120 m3 | 0.044 Person
Overseer | 0.044 Person per day x 1,120 m3 | 0.044 Person
Mountain rock | 1,200 m3 x 1,120 m3 | 1,344 Person
Sand | 0.432 x 1,120 m3 | 0.484 Person

Volume Mountain rock foundation work
Information | Amount
-|-|
Average width | (0.25 + 0.60) / 2 = 0.425 m
Length x width x height | 16.00x0,425x0,60
Amount | 4,080 m3

Coefficient 1m3 Mountain rock foundation
Information | Amount
-|-|
Workers | 1,500 Person per day
Stonemason | 0.750 Person per day
Foreman | 0.075 Person per day
Overseer | 0.075 Person per day
Mountain rock | 1,200 m3
Portland cement | 163,000 Kg
Sand pairs | 0,520 m3

Amount as needed.
Items | Information | Amount
-|-|-|
Workers | 1,500 Person per day x 4,080 m3 | 6,120 Person
Stonemason | 0.750 Person per day x 4,080 m3 | 3,060 Person
Foreman | 0.075 Person per day x 4,080 m3 | 0.306 Person
Overseer | 0.075 Person per day x 4,080 m3 | 0.306 Person
Mountain rock | 1,200 m3 x 4,080 m3 | 4,896 m3
Portland cement | 163,000 Kg x 4,080 m3 | 665,040 Kg
Sand pairs | 0.520 m3 x 4,080 m3 | 2,122 m3

CONCLUSION

At this first stage calculation we have completed the calculation
- Soil excavation
- Backfill work
- Mountain rock fondation

In accordance with the work and working drawings above then the needs of labor and materials for this stage is.

Items | Amount
-|-|
Workers | 15,501 Person
Stonemason | 3,497 Person
Foreman | 0.350 Person
Overseer | 0.633 Person
Soil | 1,779 m3
Sand | 1,373 m3
Mountain rock | 6,240 m3
Portland cement | 665,040 Kg
Sand pairs | 2,122 m3
to be continued ...

This calculation is just an example and can be used by anyone, this calculation is in accordance with technical analysis of Indonesian National Standart.[8]

Thanks to friends who have visited this blog and to scientists who are willing to sacrifice their time to realize a better civilization.

This is all I can write on this occasion, for all the mistakes and lack of writing as a servant of God, I apologize.

source:

[1] www.wikipedia.org

[2] www.wikipedia.org

[3] www.wikipedia.org

[4] www.wikipedia.org

[5] www.wikipedia.org

[6] www.wikipedia.org

[7] www.wikipedia.org

[8] www.hdesignideas.com

Do you love science? by respecting the work of others and not plagiarism then you are welcome to join steemstem by using @science tags or @SteemSTEM tags, you can also chat with us in steemit chat/steemstem channel.

https://i.imgur.com/WhYkkh9.gif

Best regards @kharrazi

TAGS: [ #engineering ] [ #science ] [ #steemstem ] [ #steemiteducation ] [ #mathematics ]

Replies

@fulsketch | Oct. 3, 2017, 5:33 p.m. | Votes: 1 | [ VOTE ]

thank you my brother has given a very good knowledge and hard to get.
by calculating work materials and labor,
whether we also need to calculate the target how many days are ready to be done ? @ kharrazi

@kharrazi | Oct. 3, 2017, 5:40 p.m. | Votes: 0 | [ VOTE ]

yes, we also have to calculate the day needed in work, because in addition to time cost becomes the determinant of work success.
thank you for stopping @fulsketch :)

@fulsketch | Oct. 3, 2017, 5:57 p.m. | Votes: 1 | [ VOTE ]

thank you brother for sharing your experience
hopefully can be useful for me :)